12/03/24
As the design developed, a collaborative approach and selection of advanced controllers with advanced communication capabilities established a failsafe solution and provided seamless integration of the existing plant to enhance redundancy. The new plant consists of three 2500-ton Chillers, three Cooling Towers, 15 Electromagnetic Inline Flowmeters, Waterside Economizer, 6 Pumps, and filtration system in a variable primary flow configuration.